What is a variation?
A variation is a change to the scope of work in a contract, such as extra work, less work or different work. The contractor records it and claims it so the contract price is adjusted.
Also known as: Contract variation, Variation claim.
How variations work in practice
Before your crew does work outside the original scope, get your client’s documented approval that it is out of scope. Agree at the same time whether the variation will be priced or done at day rates.
If it is priced, aim to have the variation approved before the work starts. When the work has to start first, get the approval as soon as you can. If the change affects the program, request an extension of time where your contract allows it.
Why variations get missed
Many legitimate variations are never claimed because nobody identifies and records them on site. Site crews can also be reluctant to raise a variation in case it strains the relationship with the client.
Good site records make the conversation about facts. Daily photos, notes on the work done, labour and equipment hours and the materials used are the evidence behind a variation request. Note anything that differs from the drawings or the scope on the day it happens.
Variations and progress claims
Approved variations are usually claimed alongside the contract works in your next progress claim. Variations done at day rates are backed up by signed dayworks dockets.