A variation is a change to the scope of work in a contract, such as extra work, less work or different work. The contractor records it and claims it so the contract price is adjusted.

Also known as: Contract variation, Variation claim.

How variations work in practice

Before your crew does work outside the original scope, get your client’s documented approval that it is out of scope. Agree at the same time whether the variation will be priced or done at day rates.

If it is priced, aim to have the variation approved before the work starts. When the work has to start first, get the approval as soon as you can. If the change affects the program, request an extension of time where your contract allows it.

Why variations get missed

Many legitimate variations are never claimed because nobody identifies and records them on site. Site crews can also be reluctant to raise a variation in case it strains the relationship with the client.

Good site records make the conversation about facts. Daily photos, notes on the work done, labour and equipment hours and the materials used are the evidence behind a variation request. Note anything that differs from the drawings or the scope on the day it happens.

Variations and progress claims

Approved variations are usually claimed alongside the contract works in your next progress claim. Variations done at day rates are backed up by signed dayworks dockets.

How Varicon helps

Raise variations as they happen and claim them on the next claim

In Varicon you raise a variation for out-of-scope work on fixed-price or day-rate contracts. Variations link to cost tracking, and once approved they are added to your next progress claim.

Approved onto the next claim

Approved variations go onto your next progress claim, and pending ones are listed for your client’s reference.

Progress claims and variations

Linked to job costs

Each variation links to cost tracking and forecasting on the job.

Progress claims and variations

Day-rate work signed on site

Dayworks dockets get your client’s signature on site or approval by email.

Dayworks dockets

  • Template

    Progress claims template

    A progress claim with a cover page for the parties and the claim summary, and a claim schedule for contract works and approved variations.

    Free download: Excel and PDF

  • Template

    Dayworks docket template

    A docket for work done on day rates, with the instruction, labour, plant and equipment, materials, and sign-off by client and contractor.

    Free download: Excel, Word and PDF

  • Guide

    Getting progress claims and variations paid

    Agree how work will be measured and approved before the job starts, keep site records that back up every claim and variation, and submit complete claims on time.

  • Glossary

    Progress claim

    A progress claim is a contractor’s request for payment for the work completed in a period, measured against the contract schedule and any approved variations.

  • Glossary

    Dayworks docket

    A dayworks docket records the labour, equipment and materials used for work that is not covered by the original contract, so the extra work can be tracked, approved and billed.

  • Glossary

    Site diary

    A site diary is a daily record of what happened on a construction site: the weather, the work done, the people and plant on site, deliveries, safety matters and anything that changed.