A progress claim is a contractor’s request for payment for the work completed in a period, measured against the contract schedule and any approved variations.

Also known as: Payment claim, Progress payment claim.

What goes into a progress claim

A claim usually lists each line of the contract schedule with:

  • the quantity, percentage or amount completed to date
  • what was claimed in earlier periods
  • what is claimed in this period
  • the balance left to complete.

Approved variations are listed the same way, then retention withheld and GST are shown in the totals. Supporting documents, such as dayworks dockets, quantity assessments and QA records, go with the claim.

Getting a claim approved

Agree with your client before the job starts how progress on each item will be measured, what supporting documents they need and how long they take to approve and pay. During the job, talk a draft through with the superintendent before you submit, and agree completed work zones as you go. Submit close to the due date with everything attached, and follow up if the claim is not approved on time.

What a claim must contain and the time limits for responding are set by your contract and by the legislation that applies where you work. Check both before you set up your claim template.

How Varicon helps

Progress claims worked out from your contract and site records

In Varicon each progress claim starts from your most recent approved claim. Enter quantity, percentage complete or a dollar amount, and Varicon works out the claim from your contract, with approved variations and retention included.

Calculated from the contract

Enter the amount for this claim or project to date, and Varicon calculates the rest from your contract.

Progress claims and variations

Versions kept in order

Manage changes as a claim is negotiated, and always work from the most recent documents.

Progress claims and variations

Dayworks ready to claim

Dayworks dockets carry claim amounts calculated as they are created, ready for approval and invoicing.

Dayworks dockets

  • Template

    Progress claims template

    A progress claim with a cover page for the parties and the claim summary, and a claim schedule for contract works and approved variations.

    Free download: Excel and PDF

  • Guide

    Getting progress claims and variations paid

    Agree how work will be measured and approved before the job starts, keep site records that back up every claim and variation, and submit complete claims on time.

  • Glossary

    Variation

    A variation is a change to the scope of work in a contract, such as extra work, less work or different work. The contractor records it and claims it so the contract price is adjusted.

  • Glossary

    Retention

    Retention is a portion of each progress payment that the client holds back as security until the work is complete and any defects are fixed.

  • Glossary

    Bank guarantee

    A bank guarantee is a promise from a contractor’s bank to pay the client up to a set amount if the contractor does not meet its obligations under the contract. It is given as security for the work.

  • Glossary

    Inspection and test plan

    An inspection and test plan (ITP) lists the inspections and tests a piece of work needs, when they happen, what the acceptance criteria are and who signs each one off.

Site-proof civil software

See how Varicon would work on your jobs

Show us how your crew and office work today. We will show you how hours, dockets and variations flow through to payroll, claims and job costs.