Progress claim and retention calculator
The original contract sum. Needed for a percent complete or a retention cap.
The contract work done to date, before retention. Leave variations out here.
How much of the contract work is done to date.
Optional. The total of approved variations, less any omissions.
The total certified in earlier claims, after retention. Enter 0 for the first claim.
The percentage held from each claim under your contract.
Optional. The most that can be held, as a percentage of the contract value.
This claim, excluding GST
- Gross value to date
- Retention held to date
- Net value to date
Working:
Enter these to see the result:
- Value of work completed to date
- Previous claims certified
- Retention
ResultEnter 3 figures to see the result.
This is an estimate. GST is not calculated, so add it as your contract requires. Your contract sets how retention and claims work, so check the result against it.
How to calculate a progress claim after retention
This claim = gross value to date − retention held − previous claims certified
A progress claim is usually worked out on the total to date, then the earlier claims are taken off.
- Gross value to date = value of work completed to date + approved variations to date. With percent complete, the work completed is contract value × percent complete.
- Retention held = gross value to date × retention %, or value of work completed × retention % when retention is held on contract work only. With a cap, it is no more than contract value × cap %.
- Net value to date = gross value to date − retention held.
- This claim = net value to date − previous claims certified.
Worked example. Work completed to date is $200,000 and approved variations are $20,000, so the gross value to date is $220,000. With 5% retention, $11,000 is held, leaving a net value to date of $209,000. Earlier claims certified $150,000, so this claim is $209,000 − $150,000 = $59,000, plus GST. If retention is held on contract work only, 5% of $200,000 is $10,000, and this claim is $60,000. Once the retention held reaches the cap, it stops growing and each later claim gets the full value of the work.
The amounts and the 5% are example figures, not typical ones.
Every dollar and percentage field starts empty. Use the figures from your contract and your last payment schedule.
What this assumes
- Retention is held on the gross value to date, or on the contract work only if you choose, up to the cap when one is entered.
- The previous claims certified are the amounts after retention.
- Bank guarantees, security, liquidated damages and back charges are not included.
How Varicon helps
Build each claim from the contract and the last approved one
This works out one claim. Varicon builds every claim from your contract and the last approved claim, adds approved variations and calculates retention as part of it.
- Claims from the contract
Enter quantity, percentage complete or a dollar amount, and Varicon calculates the claim from your contract.
- Retention and bank guarantees
Retention is calculated as part of each claim, and bank guarantees are tracked alongside.
- Dayworks ready to claim
Claim amounts are calculated as dayworks dockets are created, ready for approval and invoicing.