Forecast cost at completion calculator

Forecast from
$

The cost budget for the job or the cost code.

$

$

Your estimate of what the remaining work will cost.

$

Optional. For the forecast margin.

Enter these to see the result:

  • Budget
  • Cost to date
  • Cost to complete

This is an estimate from your own figures. A forecast is only as good as the cost to date and progress behind it, so check both are up to date.

How to calculate forecast cost at completion

Forecast = cost to date + cost to complete, or cost to date ÷ percent complete

There are two common ways to forecast a job’s final cost. Pick the one that matches what you know.

  • From cost to complete: forecast = cost to date + your estimate of the cost to complete. This is the better method when you can price the remaining work.
  • From percent complete: forecast = cost to date ÷ (percent complete ÷ 100). This assumes the remaining work costs what the work so far did, for each percent done.

Then compare it with the budget and the contract.

  • Variance to budget = budget − forecast. A negative variance is a forecast overrun.
  • Forecast margin = contract value − forecast.

Worked example, in words. A job that has spent 45% of its budget but is only 40% physically complete is heading over budget. Its forecast is the cost to date ÷ 0.4, which is 45 ÷ 40 = 1.125 times the budget: a 12.5% overrun.

Use physical progress for the percent complete, such as quantities placed. If you use cost to date ÷ budget, the forecast always equals the budget and tells you nothing.

What this assumes

  • A negative variance means the forecast is over budget.
  • The percent complete method assumes the rest of the work costs what the work so far did, for each percent done.
  • Committed costs not yet in the cost to date, such as open orders, belong in the cost to complete.

How Varicon helps

Start the forecast from the costs you already capture

This calculator works from figures you type in. Varicon gives you the actual cost side from site records, checked against your budget, so the numbers you start from are current.

Costs from site

Hours, site diaries and deliveries become job costs as they are logged, ready to compare with the budget.

Cost management

Actual cost against budget

Compare actual cost against budget by cost centre, resource type or accounting code.

Cost management

WIP and actual versus budget reports

Run WIP and actual versus budget reports, and export them to a spreadsheet to share.

Reporting and dashboards