Labour charge-out rate calculator
Charge-out rate per hour
- Cost per billable hour
- Cost per paid hour
- On-costs per paid hour
Working:
Enter these to see the result:
- Base hourly wage
- Superannuation or KiwiSaver
- Leave provision
- Workers compensation or ACC levy
- Productive hours
- Overhead
- Markup on cost
ResultEnter 7 figures to see the result.
This is an estimate from your own figures. It does not apply any award, agreement or tax rule, so check your rates and on-costs with your payroll or accounting adviser.
How to calculate a labour charge-out rate
Charge-out rate = (wage × (1 + on-costs %) + other on-costs) ÷ productive hours % × (1 + overhead %) × (1 + markup %)
A worker costs more than their wage, and not every paid hour can be charged. This calculator builds the rate up in three steps.
- Cost per paid hour = base wage × (1 + on-costs % ÷ 100) + other on-costs per hour. The on-costs are superannuation or KiwiSaver, leave, workers compensation or ACC, and payroll tax where it applies.
- Cost per billable hour = cost per paid hour ÷ (productive hours % ÷ 100). If only 80% of paid hours can be charged, each charged hour carries the cost of 1.25 paid hours.
- Charge-out rate = cost per billable hour × (1 + overhead % ÷ 100) × (1 + markup % ÷ 100).
Worked example, in words. If on-costs add a third to the wage and 80% of hours are productive, a charged hour costs 1.33 ÷ 0.8 = 1.67 times the base wage before overhead and markup. That is why a charge-out rate is often well over the hourly wage.
Every field starts empty, including the superannuation or KiwiSaver, workers compensation and payroll tax rates. Rates differ between Australia and New Zealand, between states and between businesses, so enter your own. This calculator does not interpret an award or enterprise agreement.
What this assumes
- Every on-cost percentage is taken on the base wage. Some on-costs are worked out on a different base, such as ordinary time earnings or total wages.
- Overtime, penalty rates and allowances that vary by shift are not included.
- Overhead and markup are both added to cost. Markup is not the same as margin on the sell price.
How Varicon helps
Know what every hour on site cost the job
A charge-out rate starts with the wage. Varicon captures the hours your crew works on each job, so labour costs land on the job and approved hours flow to payroll in your accounting system.
- Hours logged on site
Your crew clocks in on a phone or a shared tablet and picks the project they are on.
- Labour cost against budget
Hours your crew logs are linked to the project, so you can compare labour cost against budget.
- Charged as dayworks
An operator can turn their timesheet into a dayworks docket, priced at the rates agreed with your client.