Production rate calculator
The working days it took to complete that quantity.
The working hours it took to complete that quantity.
The full quantity for the task or the job.
Production rate
200 m³/day
Production rate
Days to complete
19 days
Hours to complete
- Quantity remaining
- 3,800 m³
- Percent complete
- 24%
Working: 1,200 m³ ÷ 6 days = 200 m³/day; 3,800 m³ to go ÷ 200 m³/day = 19 days
Production rate200 m³/day
This is an estimate at the rate achieved so far. Weather, ground conditions, access and crew changes move real production, so check it as the job goes.
How to calculate production rate and days to complete
Days to complete = (total − completed) ÷ (completed ÷ days worked)
Divide what the crew has done by the time it took, then use that rate for the rest.
- Production rate = quantity completed ÷ days (or hours) worked.
- Quantity remaining = total quantity − quantity completed.
- Days to complete = quantity remaining ÷ production rate.
- Percent complete = quantity completed ÷ total quantity × 100.
Worked example. A crew has placed 1,200 m³ of a 5,000 m³ fill in 6 days. 1,200 ÷ 6 = 200 m³ a day. 5,000 − 1,200 = 3,800 m³ to go. 3,800 ÷ 200 = 19 more working days, and the job is 24% complete.
Early days on a task are often slower while the crew sets up, so the rate can improve. Recalculate as the job goes rather than relying on the first few days.
What this assumes
- The rest of the work goes at the same rate as the work so far.
- Days to complete counts working days, not calendar days.
How Varicon helps
Know what each day on site is costing
The calculator shows how long the rest will take. Varicon records the hours, plant and materials on the job each day and costs them against the budget, so you can see where you stand.
- Costs from site
Hours, site diaries and deliveries become job costs as they are logged, ready to compare with the budget.
- Actual cost against budget
Compare actual cost against budget by cost centre, resource type or accounting code.
- Each day in the site diary
Supervisors record labour, plant, weather and progress in the site diary, and the office sees it once it is submitted.