Excavator production rate calculator

m³

The rated heaped capacity of the bucket.

%

How full the bucket gets in this material, as a percentage of its capacity.

s

One dig, swing, dump and return, in seconds. Time a few on the job.

min/h

The minutes in each hour the machine is actually digging, after delays.

%

Optional. How much bigger the material gets when dug, for the bank volume.

h

Optional. For the volume per shift.

t/m³

Optional. Tonnes per cubic metre of the loose material, for the tonnes per hour.

Loose cubic metres per hour

135 m³/h

Bank cubic metres per hour
108 m³/h
Loose cubic metres per shift
1,080 m³
Bank cubic metres per shift
864 m³

Working: 1 m³ × 90% × (3,600 ÷ 20 s) × (50 min ÷ 60) = 135 m³/h loose, ÷ (1 + 25%) = 108 m³/h bank

This is an estimate. Digging depth, swing angle, the operator and waiting for trucks all change real output, so check it against the loads you count on the job.

How to calculate excavator production rate

Loose m³ per hour = bucket × fill factor × (3,600 ÷ cycle seconds) × (working minutes ÷ 60)

An excavator’s output is the bucket load times the number of cycles it gets through in an hour.

  • Bucket load = bucket capacity × fill factor. A bucket rarely fills to its rated capacity in hard or sticky material, and can heap over it in loose, free-flowing material.
  • Cycles per hour = 3,600 ÷ cycle time in seconds.
  • Working time. No machine digs for 60 minutes every hour. Multiply by the working minutes ÷ 60 to allow for moving, waiting and short delays.
  • Bank volume = loose volume ÷ (1 + bulking % ÷ 100). This is the volume it takes out of the ground.
  • Tonnes = loose volume × loose density.

Worked example. A 1 m³ bucket, 90% fill factor, a 20 second cycle and 50 working minutes per hour. 1 × 0.9 = 0.9 m³ a bucket. 3,600 ÷ 20 = 180 cycles an hour, × 50 ÷ 60 = 150 working cycles. 0.9 × 150 = 135 loose m³ an hour. With 25% bulking, that is 135 ÷ 1.25 = 108 bank m³ an hour, and 864 bank m³ in an 8 hour shift.

The fill factor, cycle time, working minutes and bulking are example figures, not figures for any machine or material. Your own timed cycles and load counts are the best guide.

What this assumes

  • Every cycle is the same length and fills the bucket to the same fill factor.
  • The bucket volume is a loose volume. The bank volume is the loose volume less the bulking.
  • Trucks are always there to load, so the excavator never waits.

How Varicon helps

Check the rate you planned against the hours on the machine

A planned rate is a starting point. Varicon records the operator and machine hours from site and costs them to the job, so you can compare them with what you priced.

Operator hours on the job

Operators clock in on a phone or a shared tablet and pick the project and the equipment they are on.

Timesheets and payroll

Actual cost against budget

Compare actual cost against budget by cost centre, resource type or accounting code.

Cost management

Equipment prestarts

Run equipment prestart checks as forms your operators fill in on a phone, with the location recorded.

Construction forms