Skip to content

Bulking factor calculator

Convert
m³

The volume in the ground before it is dug, often from the design or a survey.

%

How much bigger the material gets when dug, as a percentage. Enter 0 for none.

Loose volume

125 m³

Bulking factor (loose ÷ bank)
1.25
Difference in volume
25 m³

Working: 100 m³ × (1 + 25%) = 125 m³

This is an estimate. Bulking changes with moisture, how the material is dug and how it is loaded, so check it against your own loads and the geotechnical report.

How to calculate bulking factor

Bulking factor = loose m³ ÷ bank m³; loose m³ = bank m³ × (1 + bulking % ÷ 100)

Material in the ground is packed tight. Dig it out and it breaks up and traps air, so the same material takes up more room on the truck or in the stockpile. That increase is the bulking, also called swell.

Volumes in the ground are bank cubic metres (BCM). Volumes once dug are loose cubic metres (LCM). To go from bank to loose, multiply by 1 plus the bulking as a decimal. To go from loose to bank, divide by the same figure.

The bulking factor is the same idea written as a ratio: loose volume ÷ bank volume. A bulking of 25% is a bulking factor of 1.25.

Worked example. You are digging out 100 m³ of material in the ground with a bulking of 25%. 100 × (1 + 0.25) = 125 m³ loose. Going back, 125 m³ ÷ 1.25 = 100 m³ in the ground.

The 25% is an example figure, not the bulking of any particular material. The material densities and bulking factors table lists typical figures, and your geotechnical report is the better source for your site.

What this assumes

  • The bank volume is the material undisturbed in the ground, and the loose volume is the same material after digging, before any compaction.
  • One bulking figure applies to the whole volume. Where the ground changes, work out each material on its own.

How Varicon helps

Track the cubic metres you actually move

Bulking tells you how much bigger the spoil gets once it is dug. Varicon records the plant and labour on the job each day and costs it against the budget, so you can see where you stand.

Plant and labour on the job

Labour, equipment and materials recorded in the site diary flow into the job’s costs.

Cost management

Actual cost against budget

Compare actual cost against budget by cost centre, resource type or accounting code.

Cost management

Each day on record

Supervisors record labour, plant, weather and progress in the site diary, and the office sees it once it is submitted.

Site diary