Haul cycle and truck numbers calculator
How long the excavator or loader takes to fill one truck.
Time at the tip or fill area to manoeuvre and dump.
Waiting at the loader and backing in. Enter 0 if trucks never wait.
Optional. For the tonnes moved per hour.
Optional. The loose volume one truck carries, for the cubic metres moved per hour.
Trucks needed, rounded up
5
- Exact trucks
- 4.63
- Cycle time per truck
- 18.5 min
- Loads per truck per hour
- 3.24 loads/h
- Moved per truck per hour
- 64.9 t/h
- Moved by the fleet per hour
- 300 t/h
- Moved per truck per hour
- Moved by the fleet per hour
Working: 4 min load + 3 km at 30 km/h (6 min) + 2 min dump + 3 km at 40 km/h (4.5 min) + 2 min queue = 18.5 min; 18.5 min ÷ 4 min = 4.63, rounded up to 5 trucks
Trucks needed, rounded up5
This is an estimate. Traffic, haul road condition, weather and delays at the loader change real cycle times, so time a few loads on the job and check it.
How to calculate the number of trucks needed
Trucks needed = cycle time ÷ load time, rounded up
A truck’s cycle is everything it does between one load and the next. Add the times together, then divide by how long the loader takes to fill one truck.
- Haul and return time = distance ÷ speed × 60, in minutes, each way.
- Cycle time = load time + haul time + dump time + return time + queue and spot time.
- Trucks needed = cycle time ÷ load time, rounded up. While one truck is loading, the rest are on the road.
- Loads per truck per hour = 60 ÷ cycle time.
- Moved per hour = payload × loads per hour. The fleet moves one payload for every load time, since the loader sets the pace.
Worked example. Load time 4 minutes, a 3 km haul at 30 km/h, 2 minutes to dump, the return at 40 km/h and 2 minutes in the queue. Haul: 3 ÷ 30 × 60 = 6 minutes. Return: 3 ÷ 40 × 60 = 4.5 minutes. Cycle: 4 + 6 + 2 + 4.5 + 2 = 18.5 minutes. Trucks: 18.5 ÷ 4 = 4.63, so 5 trucks keep the loader working. With a 20 t payload, the fleet moves 20 × 60 ÷ 4 = 300 tonnes an hour.
With one truck fewer than the figure, the loader waits for trucks. With one more, the trucks wait for the loader. The figures in the example are round numbers to show the sum, not typical times or speeds.
What this assumes
- The trucks return empty over the same distance they hauled.
- Every truck carries a full payload and the loader works every minute of the hour.
- The fleet figures assume enough trucks to keep the loader busy, so the loader sets the pace.
How Varicon helps
Book the trucks, then see who is on which job
The calculator tells you how many trucks keep the loader busy. Varicon puts crews, plant and subcontractors on one calendar, and flags double bookings before they reach site.
- Trucks and crews on one calendar
Drag workers, machines and subcontractors onto the calendar across all your jobs.
- Clashes flagged before site
Double-booked equipment, overlapping shifts and leave are flagged, so you can fix the plan first.
- Subbie hours checked
Use Varicon timesheets to tell contractors their claimable hours, and check their invoices against the hours logged.