Haul cycle and truck numbers calculator

min

How long the excavator or loader takes to fill one truck.

km

km/h

min

Time at the tip or fill area to manoeuvre and dump.

km/h

min

Waiting at the loader and backing in. Enter 0 if trucks never wait.

Payload in
t

Optional. For the tonnes moved per hour.

Trucks needed, rounded up

5

Exact trucks
4.63
Cycle time per truck
18.5 min
Loads per truck per hour
3.24 loads/h
Moved per truck per hour
64.9 t/h
Moved by the fleet per hour
300 t/h

Working: 4 min load + 3 km at 30 km/h (6 min) + 2 min dump + 3 km at 40 km/h (4.5 min) + 2 min queue = 18.5 min; 18.5 min ÷ 4 min = 4.63, rounded up to 5 trucks

This is an estimate. Traffic, haul road condition, weather and delays at the loader change real cycle times, so time a few loads on the job and check it.

How to calculate the number of trucks needed

Trucks needed = cycle time ÷ load time, rounded up

A truck’s cycle is everything it does between one load and the next. Add the times together, then divide by how long the loader takes to fill one truck.

  • Haul and return time = distance ÷ speed × 60, in minutes, each way.
  • Cycle time = load time + haul time + dump time + return time + queue and spot time.
  • Trucks needed = cycle time ÷ load time, rounded up. While one truck is loading, the rest are on the road.
  • Loads per truck per hour = 60 ÷ cycle time.
  • Moved per hour = payload × loads per hour. The fleet moves one payload for every load time, since the loader sets the pace.

Worked example. Load time 4 minutes, a 3 km haul at 30 km/h, 2 minutes to dump, the return at 40 km/h and 2 minutes in the queue. Haul: 3 ÷ 30 × 60 = 6 minutes. Return: 3 ÷ 40 × 60 = 4.5 minutes. Cycle: 4 + 6 + 2 + 4.5 + 2 = 18.5 minutes. Trucks: 18.5 ÷ 4 = 4.63, so 5 trucks keep the loader working. With a 20 t payload, the fleet moves 20 × 60 ÷ 4 = 300 tonnes an hour.

With one truck fewer than the figure, the loader waits for trucks. With one more, the trucks wait for the loader. The figures in the example are round numbers to show the sum, not typical times or speeds.

What this assumes

  • The trucks return empty over the same distance they hauled.
  • Every truck carries a full payload and the loader works every minute of the hour.
  • The fleet figures assume enough trucks to keep the loader busy, so the loader sets the pace.

How Varicon helps

Book the trucks, then see who is on which job

The calculator tells you how many trucks keep the loader busy. Varicon puts crews, plant and subcontractors on one calendar, and flags double bookings before they reach site.

Trucks and crews on one calendar

Drag workers, machines and subcontractors onto the calendar across all your jobs.

Crew and equipment scheduling

Clashes flagged before site

Double-booked equipment, overlapping shifts and leave are flagged, so you can fix the plan first.

Crew and equipment scheduling

Subbie hours checked

Use Varicon timesheets to tell contractors their claimable hours, and check their invoices against the hours logged.

Timesheets and payroll