What is forecast cost to complete (FCTC)?
Forecast cost to complete (FCTC) is the expected final cost of a project, worked out from what has been spent so far and the remaining quantities and unit rates.
Also known as: FCTC.
How it works
A forecast starts from the budget and the costs already on the job. For the work still to do, it uses the remaining quantities and the unit rates you expect to achieve, which is where production tracking comes in. Compare the forecast with the contract value and you can see the margin the job is heading for while there is still time to act.
A forecast needs judgement as well as numbers. The project manager should be able to adjust it for conditions the budget and production data do not show, such as a wet month ahead or a known design change.