What is forecast cost to complete (FCTC)?

Forecast cost to complete (FCTC) is the expected final cost of a project, worked out from what has been spent so far and the remaining quantities and unit rates.

Also known as: FCTC.

How it works

A forecast starts from the budget and the costs already on the job. For the work still to do, it uses the remaining quantities and the unit rates you expect to achieve, which is where production tracking comes in. Compare the forecast with the contract value and you can see the margin the job is heading for while there is still time to act.

A forecast needs judgement as well as numbers. The project manager should be able to adjust it for conditions the budget and production data do not show, such as a wet month ahead or a known design change.

How Varicon helps

A forecast is only as good as the costs to date

Varicon does not produce the forecast. It gives you the costs to date that a forecast starts from: actual cost by cost centre from site records, checked against your budget.

Costs from site

Hours, site diaries and deliveries become job costs as they are logged, ready to compare with the budget.

Cost management

Actual cost against budget

Compare actual cost against budget by cost centre, resource type or accounting code.

Cost management

WIP and actual versus budget reports

Run WIP and actual versus budget reports, and export them to a spreadsheet to share.

Reporting and dashboards

  • Guide

    Managing job costs on civil construction projects

    Break each job into cost codes, capture labour, plant and materials against them every day, count supplier costs when the goods arrive, claim every variation, and use what each job teaches you in your next tender.

  • Glossary

    Production tracking

    Production tracking measures how much work is done on each task, as quantities or percentage complete, and compares the actual cost per unit with the budget.

  • Glossary

    Cost code

    A cost code is a label for a part of a job, such as bulk earthworks or drainage, that costs are allocated to, so you can compare actual cost with the budget for that part of the job.

  • Glossary

    WIP report

    A work in progress (WIP) report shows, for each job that is still running, the costs and claims to date against the contract value and the forecast final cost, so you can see where each job stands.

  • Glossary

    Earned value

    Earned value compares the budgeted value of the work actually done with what that work cost and with what was planned to be done by now, to show whether a job is over or under budget and ahead or behind.

  • Glossary

    Margin erosion

    Margin erosion is the gradual loss of the profit margin on a job, as costs creep above what the price allowed for, often in small amounts that are not noticed until the job is finished.

Site-proof civil software

See how Varicon would work on your jobs

Show us how your crew and office work today. We will show you how hours, dockets and variations flow through to payroll, claims and job costs.