What is earned value?
Earned value compares the budgeted value of the work actually done with what that work cost and with what was planned to be done by now, to show whether a job is over or under budget and ahead or behind.
Also known as: Earned value analysis.
The three numbers
- Planned value is the budget for the work that should have been done by now.
- Earned value is the budget for the work that has actually been done.
- Actual cost is what the work done has actually cost.
Reading them
If earned value is less than actual cost, the work done has cost more than its budget. If earned value is less than planned value, less work has been done than planned.
Looking at cost alone can mislead. A job that has spent less than planned may simply be behind, and earned value shows which it is. It depends on measuring progress honestly, which is what production tracking is for.