Earned value compares the budgeted value of the work actually done with what that work cost and with what was planned to be done by now, to show whether a job is over or under budget and ahead or behind.

Also known as: Earned value analysis.

The three numbers

  • Planned value is the budget for the work that should have been done by now.
  • Earned value is the budget for the work that has actually been done.
  • Actual cost is what the work done has actually cost.

Reading them

If earned value is less than actual cost, the work done has cost more than its budget. If earned value is less than planned value, less work has been done than planned.

Looking at cost alone can mislead. A job that has spent less than planned may simply be behind, and earned value shows which it is. It depends on measuring progress honestly, which is what production tracking is for.

How Varicon helps

Earned value needs actual costs you can trust

Earned value compares planned work, work done and actual cost. Varicon gives you the actual cost, by cost centre from the records your crew logs on site, checked against your budget.

Costs from site

Hours, site diaries and deliveries become job costs as they are logged, ready to compare with the budget.

Cost management

Actual cost against budget

Compare actual cost against budget by cost centre, resource type or accounting code.

Cost management

WIP reports

Run WIP and actual versus budget reports, and export them to a spreadsheet to share.

Reporting and dashboards

  • Guide

    Managing job costs on civil construction projects

    Break each job into cost codes, capture labour, plant and materials against them every day, count supplier costs when the goods arrive, claim every variation, and use what each job teaches you in your next tender.

  • Glossary

    Production tracking

    Production tracking measures how much work is done on each task, as quantities or percentage complete, and compares the actual cost per unit with the budget.

  • Glossary

    WIP report

    A work in progress (WIP) report shows, for each job that is still running, the costs and claims to date against the contract value and the forecast final cost, so you can see where each job stands.

  • Glossary

    Forecast cost to complete

    Forecast cost to complete (FCTC) is the expected final cost of a project, worked out from what has been spent so far and the remaining quantities and unit rates.