What is a WIP report in construction?

A work in progress (WIP) report shows, for each job that is still running, the costs and claims to date against the contract value and the forecast final cost, so you can see where each job stands.

Also known as: Work in progress report.

What a WIP report usually shows

For each job:

  • the contract value, including approved variations
  • the cost to date
  • the forecast final cost
  • the amount claimed to date
  • the expected margin.

Read across all jobs, it shows which jobs are on track, which are slipping, and whether you have claimed more or less than the work done so far.

Why it matters

A WIP report puts every running job on one page. It is often the first report an owner, a finance manager or the bank asks for, and it is only as good as the cost and progress data behind it. Your accountant can tell you how they want WIP worked out for your financial reports.

How Varicon helps

Run your WIP report without building the spreadsheet

A WIP report is only as good as the cost and progress behind it. Varicon runs WIP reports from the data your crew and office already capture, so you can see where you stand on every job.

WIP and actual versus budget

Run WIP reports alongside actual versus budget comparisons.

Reporting and dashboards

Export to a spreadsheet

Download any report you have run as a spreadsheet, to analyse further or share with others.

Reporting and dashboards

Costs from site

Hours, site diaries and deliveries become job costs as they are logged.

Cost management

  • Guide

    Managing job costs on civil construction projects

    Break each job into cost codes, capture labour, plant and materials against them every day, count supplier costs when the goods arrive, claim every variation, and use what each job teaches you in your next tender.

  • Glossary

    Forecast cost to complete

    Forecast cost to complete (FCTC) is the expected final cost of a project, worked out from what has been spent so far and the remaining quantities and unit rates.

  • Glossary

    Earned value

    Earned value compares the budgeted value of the work actually done with what that work cost and with what was planned to be done by now, to show whether a job is over or under budget and ahead or behind.

  • Glossary

    Progress claim

    A progress claim is a contractor’s request for payment for the work completed in a period, measured against the contract schedule and any approved variations.

Site-proof civil software

See how Varicon would work on your jobs

Show us how your crew and office work today. We will show you how hours, dockets and variations flow through to payroll, claims and job costs.