Managing job costs on civil construction projects
Break each job into cost codes, capture labour, plant and materials against them every day, count supplier costs when the goods arrive, claim every variation, and use what each job teaches you in your next tender.
- Published
- Reading time
- 3 min read

Why one bucket of money does not work
Many contractors run each job as one bucket of money, with costs going out and progress payments coming in. In reality a job is a set of smaller pieces of work, each with its own budget. Go over budget on one and it is hard or impossible to make it up on another.
The usual causes of overruns are inefficiencies that better planning would fix, changes in scope that should have been claimed as variations, and errors in the original estimate. You can only act on them if you see them while the job is running.
Step 1: set up cost codes
Allocate every cost to a cost code, also called a cost centre: a high-level task such as bulk earthworks, drainage, concreting, asphalting or overheads. The more detail you track, the more work it is for your crew, so start simple. Varicon’s advice is to aim for 5 to 10 cost codes, depending on the size of the job.
Step 2: capture costs on site, every day
Labour, plant and materials should be recorded against the job and the cost code on the day they are used. That means timesheets with the project and equipment for each worker, a site diary for plant and materials, and delivery dockets for what arrives. Check each cost code against its budget regularly, not only at month end.
Step 3: count committed costs when the goods arrive
Materials and subcontractors are usually the biggest costs on a civil job, and the bills often arrive weeks after the goods. If you only count a cost when the invoice turns up, your job costs are out of date and you do not know how much cash you will need to pay what you owe. Contractors who win a lot of work can get into trouble this way, because their working capital does not keep up.
Raise purchase orders for suppliers and subcontractors, work out the committed cost from the agreed rates, and keep the dockets with the order. Your office then knows what bills to expect, and checking them is quick when they arrive.
Step 4: claim every variation
Tender documents are full of assumptions, and any change from them should be claimed as a variation. In practice many legitimate variations are missed because nobody identifies and records them on site, sometimes because the crew does not want to strain the relationship with the client.
Keep daily photos, notes on the work done, labour and equipment hours and the materials used for each major task, and note anything that differs from the original agreement. A variation request backed by records is a conversation about facts, which is quicker to approve and easier on the relationship.
Step 5: stop typing the same thing twice
Every time the same information is typed into another system, it costs admin time, adds a chance for error and slows down the people who need it. Review how these connect in your business:
- estimating
- daily diaries and timesheets
- purchase orders and supplier dockets
- job cost tracking and approvals
- management reporting and accounting.
Where you can, replace paper with digital tools that work on a phone or a tablet and are simple enough for your crew to use.
Step 6: track production and forecast the finish
Total cost to date does not tell you whether a job is on track. Production tracking compares actual and budgeted cost per unit, such as per cubic metre or tonne, so you can see which tasks are ahead or behind. A forecast cost to complete uses what is left to do to estimate the final cost, so you can see the margin a job is heading for.
Step 7: feed the results into your next tender
Your biggest financial risk is in estimating. Price too high and you lose the tender, too low and you lose money. At the end of each job, compare the actual costs with the estimate and ask:
- What changed since the original estimate?
- What did we get right, and what did we get wrong?
- What should we change in our estimating assumptions for the next tender?