Test turnaround times

Typical test turnaround times
TestTest methodFixed by the methodTypical time to a resultWhat changes itSources
Field density by nuclear gaugeAS 1289.5.8.1A reading on site straight away, in about a minute. The official result, the relative compaction, also needs the lab’s maximum dry density, so it takes longer.3 days or more for the official resultWhether the maximum dry density is already known, or found the same day by the Hilf method.

1

Maximum dry density and optimum moisture, standard compactionAS 1289.5.1.1Curing the moistened sample before it is compacted, from 2 hours for sands to 7 days for high-plasticity clays in the Queensland method.2 to 4 daysThe material. Road base gravels are quicker than heavy clays.

2, 3

Maximum dry density and optimum moisture, modified compactionAS 1289.5.2.1Curing the moistened sample before it is compacted, from 2 hours for sands to 7 days for high-plasticity clays in the Queensland method.2 to 4 daysThe material. Road base gravels are quicker than heavy clays.

2, 3

Hilf density ratio (rapid method)AS 1289.5.7.1Worked out from the field sample without finding its moisture content first.Up to 1 working dayThe lab’s queue, how many samples arrive at once and transport to the lab.

4, 5

CBR, soakedAS 1289.6.1.1Usually 4 days soaking after the sample is compacted, plus curing before that.7 to 10 daysHow long the material must cure before it is compacted, which is longer for clays, then the lab’s queue.

6, 7

Particle size distribution by sievingAS 1289.3.6.1Drying the sample in an oven to a constant mass.1 to 2 daysThe fines in the sample. A hydrometer analysis for clay takes 5 to 7 days.

2, 3

Atterberg limits and plasticity indexAS 1289.3.1.1, 3.2.1 and 3.3.1Queensland’s liquid limit method cures the moistened soil for at least 12 hours before testing.3 to 4 daysThe material. Heavy clays take the longest.

2, 3

Linear shrinkageAS 1289.3.4.1Drying the soil bar in its mould to a constant mass in an oven.24 hoursThe lab’s queue, how many samples arrive at once and transport to the lab.

8, 3

Concrete slumpAS 1012.3.1Done on site at delivery, with the result straight away.Same dayHow soon the tester sends the field report.

9

Concrete compressive strength, 7 daysAS 1012.8.1 and AS 1012.9Cylinders are cured, then crushed at the age the spec sets. 7 days is an early check.7 daysCollecting the cylinders from site. The result is reported the day they are crushed.

9, 10

Concrete compressive strength, 28 daysAS 1012.8.1 and AS 1012.9Cylinders are cured, then crushed at 28 days, the age the spec sets strength at.28 daysThe age itself cannot be shortened. The result is reported the day the cylinders are crushed.

9, 10

Asphalt core density and air voidsAS 2891.1.2, AS/NZS 2891.8 and AS/NZS 2891.9.2Cores are cut from the finished layer, then density and air voids are measured in the lab.1 to 3 working daysCoring crew bookings, then the lab’s queue.

11, 12

Dynamic cone penetrometerAS 1289.6.3.2A field test of about 10 minutes, read as it is done.Up to 1 dayHow soon the tester sends the report.

1

Plate load testAs named in the project specAbout an hour on site for each test, against a reaction load you provide.1 dayArranging the reaction load, and the tester’s program.

1

These are typical times for planning. Ask your testing lab for its current turnaround, and allow time for sampling, transport and reporting.

About these figures

Some of a test’s time is fixed by the test method itself. A 28-day concrete strength result cannot come back before the cylinders are 28 days old, and a soaked CBR needs at least four days in the water. The rest is the lab’s queue, sample preparation, checking and reporting, which changes from lab to lab and week to week.

The table shows both, so you can see which part you can plan around and which part you can ask the lab to speed up. Lab figures are the time the test itself needs, as published by the named lab or authority. The lab’s queue comes on top.

Field tests such as nuclear density gauge readings and slump tests give a reading on site, but the signed report can follow later. Plan hold points around the time the result is reported, not the time the test is done.

Every row names the public sources it was read from: the first for the time to a result, the rest for the method or the fixed part.

How Varicon helps

Keep test results with the rest of the job record

Turnaround sets how long you wait for results. Varicon keeps the day-to-day record around them: inspection forms filled in on site, and a site diary with photos and notes.

Site inspections as forms

Build site inspection and hazard report forms, and your crew fills them in on a phone or a tablet.

Construction forms

Photos and notes in the site diary

Add photos of site conditions and progress, and notes on events, observations and conversations.

Site diary

Forms routed to the right people

Route each form to the right people, set auto-approvals and trigger the next step.

Construction forms