Reinforcing mesh sheet calculator

m

The side the sheet length runs along.

m

m

m

mm

The overlap where the ends of two sheets meet, from your drawings.

mm

The overlap where the sides of two sheets meet, from your drawings.

%

For openings, penetrations and spoiled sheets. The layout already counts part sheets at the edges as whole sheets.

Sheets to order

20

Sheets along the slab
4
Rows across the slab
5
Sheets laid
20
Slab area
200 m²

Working: Along: (20 m − 0.2 m) ÷ (6 m − 0.2 m) = 3.41, so 4. Across: (10 m − 0.2 m) ÷ (2.4 m − 0.2 m) = 4.45, so 5. 4 × 5 = 20 sheets

This is an estimate for a rectangular slab. Openings, steps and an L-shaped slab change the real count, so check it against your layout before you order.

How to calculate the number of mesh sheets

Sheets = sheets along the slab × rows across the slab, plus waste, rounded up

Lay the sheets out the way your crew would. The first sheet in a run covers its full length, and each sheet after it adds its length less the lap. So the sheets along the slab are (slab length − end lap) ÷ (sheet length − end lap), rounded up. The rows across are (slab width − side lap) ÷ (sheet width − side lap), rounded up. Multiply the two, then add any waste allowance for openings and round up. The laps are in millimetres, so divide them by 1,000.

Worked example. A slab 20 m by 10 m, with 6.0 m by 2.4 m sheets and 200 mm laps on the ends and sides. Along: (20 − 0.2) ÷ (6.0 − 0.2) = 3.41, so 4 sheets. Across: (10 − 0.2) ÷ (2.4 − 0.2) = 4.45, so 5 rows. 4 × 5 = 20 sheets.

The last sheet in each run and the last row are part sheets, cut to fit. That is why a layout count is higher than dividing the slab area by the area one sheet covers, which gives 16 sheets here and leaves the edges short.

The laps are example figures. Take the laps from your drawings, since they depend on the mesh and the design.

What this assumes

  • The slab is a rectangle, and the sheets run with their length along the slab length.
  • Each sheet after the first in a run adds its size less the lap. Part sheets at the edges count as whole sheets, and offcuts are not reused.
  • Laps come from your drawings or engineer. The 200 mm in the example is not a design lap.

How Varicon helps

Order the mesh, then track the delivery and the cost

The calculator gives you the sheets to order. Varicon tracks the purchase order, the delivery docket and the supplier bill, and puts the cost on the job.

Purchase orders raised on site

Your field team can raise a purchase order for a specific job in the Varicon mobile app.

Accounts payable

Docket costed on arrival

Your crew captures the delivery docket on site, and the cost is recorded against the job when the mesh arrives.

Delivery dockets

Actual cost against budget

Compare actual cost against budget by cost centre, resource type or accounting code.

Cost management