Road base and gravel calculator
The depth of the layer once compacted.
Tonnes per cubic metre once compacted in place.
For edges, uneven subgrade and spillage. Adjust it to suit the job, or enter 0 for none.
Loose volume ÷ compacted volume. Leave it blank if you order by the tonne only.
Tonnes to order
126 t
- Compacted volume
- 60 m³
- Loose volume to order
- 81.9 m³
- Area
- 400 m²
Working: 50 m × 8 m × 150 mm ÷ 1,000 × 2 t/m³ × (1 + 5%) = 126 t
Tonnes to order126 t
This is an estimate. Moisture, grading and how hard the layer is rolled change the real figure, so check it against your supplier and your dockets.
How to calculate road base and gravel quantities
Tonnes to order = area × compacted depth × compacted density, plus the waste allowance
Work out the compacted volume first: area × compacted depth. Convert the depth from millimetres to metres by dividing by 1,000. Multiply the compacted volume by the compacted density for the tonnes in place, then add the waste allowance for the tonnes to order.
If you order by the cubic metre, multiply the compacted volume by the compaction factor instead. That gives the loose volume, and the waste allowance is added to it as well.
Worked example. A pad 50 m by 8 m, 150 mm deep once compacted, at a compacted density of 2.0 t/m³ with a 5% waste allowance. 50 × 8 = 400 m², and 400 × 0.15 = 60 m³ compacted. 60 × 2.0 × 1.05 = 126 tonnes to order. With a compaction factor of 1.3, the loose volume to order is 60 × 1.3 × 1.05 = 81.9 m³.
The density, compaction factor and waste allowance are example figures, not the figures for any particular product. Use your supplier’s figures, or the material densities and bulking factors table.
What this assumes
- The layer has the same compacted depth across the whole area.
- The density is the compacted density in place, and the compaction factor is the loose volume divided by the compacted volume.
- The waste allowance is added to both the tonnes and the loose volume to order, not to the compacted volume.
How Varicon helps
Check every load of road base against the order
The calculator gives the tonnes to order. Varicon captures each delivery docket on site and matches the supplier bill to it and the purchase order, so you can confirm the tonnes before you pay.
- Delivery dockets captured on site
Your crew captures each delivery docket on a phone as the load arrives, with any supporting documents.
- Matched to the purchase order
The supplier bill is matched to its purchase order and delivery docket, so you can confirm it is right before you pay.
- Costed to the job on arrival
A delivery docket creates a cost against the job when the delivery arrives, before the supplier invoice.