Pipe fall and grade calculator
The horizontal distance between the two ends, such as pit to pit.
For a grade of 1 in 100, enter 100.
The drop in level from one end to the other.
Optional. The level of the inside bottom of the pipe at the high end.
Fall
400 mm
Grade
- Fall in metres
- 0.4 m
- Grade, 1 in
- 100
- Downstream invert level
- 24.6 m
Working: 40 m × 1% = 0.4 m. Downstream invert: 25 m − 0.4 m = 24.6 m
Fall400 mm
The sum is exact. Your design and the minimum grades it calls for come first, so check the levels against the drawings before you lay.
How to calculate pipe fall and grade
Fall = length × grade % ÷ 100, or length ÷ X for a grade of 1 in X
The fall is the length times the grade. With a grade in percent, fall = length × percent ÷ 100. With a grade of 1 in X, fall = length ÷ X.
To find the grade from a fall, divide the fall by the length. In percent, grade = fall ÷ length × 100. As 1 in X, X = length ÷ fall.
The downstream invert level is the upstream invert level less the fall.
Worked example. A 40 m run at a grade of 1%. 40 × 1 ÷ 100 = 0.4 m, or 400 mm of fall. That is a grade of 1 in 40 ÷ 0.4 = 1 in 100. With an upstream invert level of 25.000 m, the downstream invert level is 25.000 − 0.400 = 24.600 m.
What this assumes
- The pipe runs at one even grade from end to end.
- The length is the horizontal distance. At pipe grades it is close enough to the length along the pipe.
- Levels are in metres on the same datum, and can be below zero.
How Varicon helps
Keep a record of the pipe work as it goes in
The calculator checks fall and invert levels. Varicon does not set out pipes, but it keeps the record of the work: inspection forms, photos and notes in the site diary.
- Inspection forms on site
Build inspection checklists without code, and your crew completes them on a phone with the location recorded.
- Photos and notes in the site diary
Add photos of site conditions and progress, and notes on events, observations and conversations.
- Plant and labour on the job
Labour, equipment and materials recorded in the site diary flow into the job’s costs.