5 civil construction tips to streamline your progress claims and variation claims

Published
Updated
Reading time
3 min read
Page of a Varicon progress claim PDF with tables for contract works, approved variations and pending variations

One of the biggest challenges for our customers is getting paid in full and on time for completed work. Late or short payment strains cash flow and cuts margins. In the worst cases, and there are too many, it puts contractors out of business. It also strains the relationship with your client.

Varicon’s founder spent a decade in civil construction, in contractor, asset owner and superintendent roles, and lived this problem before setting out to solve it.

The good news is that a few simple practices go a long way. They add very little work for your team.

1. Get clear on how the contract will run

Talk to the person who assesses your claims, and do it before the project starts. With rare exceptions, most superintendents want to administer your contract fairly, and problems come from being out of step.

Questions to ask:

  • How will completed work be assessed? By the contractor and superintendent together, or by a quantity surveyor?
  • What documents do you need from us to support claims?
  • What are the timeframes, so progress payments are not delayed?
  • For out-of-scope work, what approvals do you need before we start, and what documents after we finish?
  • What else can we do to make our claims easier to assess and approve?

If you make their job easier, you get paid faster and build a better relationship.

2. Have a system for claims and site records

A lot happens during construction, and without a good system things get messy fast. Keep one place, with version control, for:

These matter most in a dispute. Most disputes can be prevented with good communication and documentation. If you still end up in one, these records help you resolve it much faster.

A system like Varicon keeps progress claims and variations in one place, built from the records your crew already keeps.

3. Work with your superintendent before you claim

Where you can, work through a claim with your superintendent before you submit it formally. How you do this depends on the work and your contract conditions.

It can be informal, such as sending your draft calculations or having a conversation to make sure you agree.

4. Manage variations and dayworks by the contract

Poorly managed variations and dayworks are a major cause of payment problems. To prevent them:

  • Before doing any work outside the original scope, get documented client approval, an acknowledgement that it is out of scope, and agreement on whether the variation is priced or on day rates.
  • If it is priced, ideally get the variation approved before you start. That is not always possible, so if you start without approval, get it as soon as you can.
  • Request an extension of time if one applies.
  • For dayworks, fill in dayworks dockets for the superintendent to sign. If they are not on site, at least send them the docket and any supporting documents.
  • If dockets are not signed on the spot, keep a record of the correspondence, so you can claim the amounts if approval is not given within the time the contract requires.

If your contract is entirely dayworks, it is not a blank cheque to do whatever you think is needed:

  • Working under a head contractor, their responsible person, such as the supervisor or project manager, usually tells you what work to do.
  • Working as the head contractor, make sure you have documents approving the scope of work to be done on dayworks.

5. Follow good practice for progress and variation claims

Good practice makes your claims easier to assess and approve, and gives you more legal recourse in a dispute.

Things to consider:

  • Make sure your claims and variations comply with the contract and the security of payment legislation in your state.
  • Use version control so you always work from the latest documents.
  • Include supporting documents in a format your client can review easily, such as dayworks dockets, quantity assessments and QA records.
  • Submit claims on time, and follow up if they are not approved on time.

You can manage all of this with a well-organised system in Excel or similar. Our free progress claims template is a good start. If you want to keep it easy, book a demo and talk to us about whether Varicon can help with your contract management.

How Varicon helps

Claim from the contract, with the dayworks and diary behind it

Tip 2 is a system for claims and site records. In Varicon each claim is worked out from your contract and the last approved claim, and the dockets and diaries that back it up are recorded on site.

Claims worked out from the contract

Enter quantity, percentage complete or a dollar amount, and Varicon calculates the claim, with approved variations added.

Progress claims and variations

Dayworks signed on the day

Your client representative signs the docket on the device on site, or approves it by email.

Dayworks dockets

A record of every day on site

Weather, photos, labour, equipment, issues and progress, recorded on site in the site diary.

Site diary

  • Template

    Progress claims template

    A progress claim with a cover page for the parties and the claim summary, and a claim schedule for contract works and approved variations.

    Free download: Excel and PDF

  • Template

    Dayworks docket template

    A docket for work done on day rates, with the instruction, labour, plant and equipment, materials, and sign-off by client and contractor.

    Free download: Excel, Word and PDF

  • Guide

    Getting progress claims and variations paid

    Agree how work will be measured and approved before the job starts, keep site records that back up every claim and variation, and submit complete claims on time.

  • Glossary

    Progress claim

    A progress claim is a contractor’s request for payment for the work completed in a period, measured against the contract schedule and any approved variations.

  • Glossary

    Variation

    A variation is a change to the scope of work in a contract, such as extra work, less work or different work. The contractor records it and claims it so the contract price is adjusted.

  • Glossary

    Dayworks docket

    A dayworks docket records the labour, equipment and materials used for work that is not covered by the original contract, so the extra work can be tracked, approved and billed.

Site-proof civil software

See how Varicon would work on your jobs

Show us how your crew and office work today. We will show you how hours, dockets and variations flow through to payroll, claims and job costs.