5 civil construction tips to streamline your progress claims and variation claims
- Published
- Updated
- Reading time
- 3 min read

One of the biggest challenges for our customers is getting paid in full and on time for completed work. Late or short payment strains cash flow and cuts margins. In the worst cases, and there are too many, it puts contractors out of business. It also strains the relationship with your client.
Varicon’s founder spent a decade in civil construction, in contractor, asset owner and superintendent roles, and lived this problem before setting out to solve it.
The good news is that a few simple practices go a long way. They add very little work for your team.
1. Get clear on how the contract will run
Talk to the person who assesses your claims, and do it before the project starts. With rare exceptions, most superintendents want to administer your contract fairly, and problems come from being out of step.
Questions to ask:
- How will completed work be assessed? By the contractor and superintendent together, or by a quantity surveyor?
- What documents do you need from us to support claims?
- What are the timeframes, so progress payments are not delayed?
- For out-of-scope work, what approvals do you need before we start, and what documents after we finish?
- What else can we do to make our claims easier to assess and approve?
If you make their job easier, you get paid faster and build a better relationship.
2. Have a system for claims and site records
A lot happens during construction, and without a good system things get messy fast. Keep one place, with version control, for:
- progress claims
- variation requests
- dayworks
- daily site records.
These matter most in a dispute. Most disputes can be prevented with good communication and documentation. If you still end up in one, these records help you resolve it much faster.
A system like Varicon keeps progress claims and variations in one place, built from the records your crew already keeps.
3. Work with your superintendent before you claim
Where you can, work through a claim with your superintendent before you submit it formally. How you do this depends on the work and your contract conditions.
It can be informal, such as sending your draft calculations or having a conversation to make sure you agree.
4. Manage variations and dayworks by the contract
Poorly managed variations and dayworks are a major cause of payment problems. To prevent them:
- Before doing any work outside the original scope, get documented client approval, an acknowledgement that it is out of scope, and agreement on whether the variation is priced or on day rates.
- If it is priced, ideally get the variation approved before you start. That is not always possible, so if you start without approval, get it as soon as you can.
- Request an extension of time if one applies.
- For dayworks, fill in dayworks dockets for the superintendent to sign. If they are not on site, at least send them the docket and any supporting documents.
- If dockets are not signed on the spot, keep a record of the correspondence, so you can claim the amounts if approval is not given within the time the contract requires.
If your contract is entirely dayworks, it is not a blank cheque to do whatever you think is needed:
- Working under a head contractor, their responsible person, such as the supervisor or project manager, usually tells you what work to do.
- Working as the head contractor, make sure you have documents approving the scope of work to be done on dayworks.
5. Follow good practice for progress and variation claims
Good practice makes your claims easier to assess and approve, and gives you more legal recourse in a dispute.
Things to consider:
- Make sure your claims and variations comply with the contract and the security of payment legislation in your state.
- Use version control so you always work from the latest documents.
- Include supporting documents in a format your client can review easily, such as dayworks dockets, quantity assessments and QA records.
- Submit claims on time, and follow up if they are not approved on time.
You can manage all of this with a well-organised system in Excel or similar. Our free progress claims template is a good start. If you want to keep it easy, book a demo and talk to us about whether Varicon can help with your contract management.